A. 1/4
B. 1/10
C. 7/15
D. 8/15
Answer: D
B. 1/10
C. 7/15
D. 8/15
Answer: D
Explanation:
A's 1 day's work = 1/15;
B's 1 day's work = 1/20;
(A + B)'s 1 day's work = (1/15 + 1/20) = 7/60
(A + B)'s 4 day's work = (7/60 x 4) = 7/15
Therefore, Remaining work = (1 - 7/15) = 8/15
B's 1 day's work = 1/20;
(A + B)'s 1 day's work = (1/15 + 1/20) = 7/60
(A + B)'s 4 day's work = (7/60 x 4) = 7/15
Therefore, Remaining work = (1 - 7/15) = 8/15